Obtain precise dimensions, weight, center of gravity, and lifting points of all components. Include detailed CAD drawings and weight distribution calculations. Specify material composition for accurate density calculations.
Identify suitable ports with adequate infrastructure (cranes with sufficient lifting capacity, quayside capacity exceeding the dimensions of the largest module, heavy-lift equipment availability, sufficient draft for the chosen vessel). Consider proximity to the Manufacturing site and final destination to minimize land transport costs and risks. Conduct a thorough assessment of port handling capabilities and potential congestion issues.
Choose a heavy-lift vessel with sufficient lifting capacity and deck space. Consider vessel types: heavy-lift ships (e.g., with cranes capable of lifting multiple hundreds of tons), semi-submersible heavy-lift vessels (for exceptionally large and heavy modules), and specialised barge solutions. Evaluate factors like stability, seaworthiness, and transit time. Obtain vessel specifications and ensure compliance with relevant regulations (e.g., IMO).
Determine the optimal shipping route, considering weather conditions (seasonal patterns, potential for storms), canal transit restrictions (Panama Canal, Suez Canal – dimensions and draft limitations), and potential delays (port congestion, political instability). Utilize specialised software for route optimization and risk assessment. Develop contingency plans for alternative routes.
Define the optimal module sizes for efficient transport and handling. Balance module size with transportation constraints (weight, dimensions, handling capabilities). Consider the feasibility of pre-assembly at the Manufacturing site to reduce on-site assembly time at the destination. Develop a detailed modularization plan with 3D models.
Develop a detailed plan for securing modules on the vessel, complying with all relevant regulations (e.g., IMO, SOLAS). Specify lashing materials (e.g., high-tensile steel wire ropes, chains, and lashing systems). Include detailed calculations to ensure sufficient securing force under various sea conditions. Use experienced riggers to oversee the lashing process.
Obtain all necessary permits and approvals from relevant authorities (port authorities, customs, maritime agencies, national and international regulatory bodies). This includes permits for oversized loads, special cargo handling, and any necessary environmental impact assessments.
Secure comprehensive cargo insurance covering all risks associated with OOG cargo transport. This should include coverage for damage, loss, and delays. Ensure adequate coverage for the total value of the substation and associated costs.
Plan for the transport of smaller, ancillary components as Breakbulk, ensuring synchronized arrival with the main modules. Utilize appropriate packaging and handling methods to prevent damage during transit. Track Breakbulk shipments separately and ensure timely delivery to the destination.
Utilize specialised heavy-lift trailers for land transport to and from the port. Obtain necessary permits for oversized loads, including route permits and escort vehicle requirements. Consider trailer specifications (axle configuration, load capacity) to match the weight and dimensions of the modules.
Conduct thorough route surveys to identify any potential obstacles or restrictions (bridges, tunnels, overhead power lines). Plan the route to minimize risks and ensure safe passage. Coordinate with local authorities to obtain necessary clearances and permissions.
Employ escort vehicles for safety and compliance with regulations. Escort vehicles provide guidance, warning, and support during transport. Ensure escort drivers are trained and equipped to handle oversized load transport.
Utilize heavy-lift cranes on the quayside and onboard the vessel for loading and unloading. Ensure cranes have sufficient lifting capacity and reach. Coordinate crane operations carefully to prevent damage to the modules or the vessel.
Employ robust lashing systems to secure modules against movement during transit. This should be overseen by experienced riggers. Use appropriate lashing materials and techniques to ensure secure fastening. Regularly inspect lashings during transit to ensure they remain secure.
Ensure even weight distribution on the vessel's deck to maintain stability. Utilize weight distribution calculations and diagrams to optimize load placement. Monitor weight distribution throughout the loading process.
Monitor the vessel's progress and environmental conditions throughout the voyage. Utilize GPS tracking and weather monitoring systems. Stay informed about potential risks and adjust plans as needed.
Maintain constant communication with the vessel's crew and relevant stakeholders. Use various communication channels (satellite phone, email, etc.) to ensure timely information exchange.
Utilize heavy-lift cranes at the destination port for unloading. Coordinate crane operations with land transport arrangements. Ensure safe and efficient unloading procedures.
Arrange for heavy-lift trailers to transport modules to the final destination. Repeat route surveys and obtain necessary permits for oversized loads.
Ensure accurate and complete documentation, including detailed cargo specifications, weight, dimensions, and handling instructions. Maintain multiple copies of the bill of lading.
Maintain copies of all insurance certificates. Ensure insurance coverage is adequate and covers all potential risks.
Keep records of all port clearances and permits. Maintain organized records for auditing and compliance purposes.
Information regarding Shipping International's logistics expertise can be found here: shippinginternational.co.uk,